Union Station - Northwest PATH
Federal contribution
$433,347
Federal share47%
of $928.5K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedOct 13, 2017
201820192020
Built
Approved 3 months before the announcement.
- Program
- Public Transit Infrastructure Fund
- Ultimate recipient
- City of Toronto
- Construction start
- Apr 1, 2017(actual)
- Construction end
- Mar 1, 2020(actual)
Against the original forecast
- Construction start4 weeks lateforecast Mar 1, 2017
- Construction end4 weeks earlyforecast Mar 31, 2020