Middletown Crossing Highway 3/43 Intersection Improvements
Federal contribution
$2.6M
$2,558,733
Federal share33%
of $7.7M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 11, 2017
20182019
Built
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- District of Sparwood
- Construction start
- Apr 11, 2017(actual)
- Construction end
- Dec 14, 2018(actual)
Also in Sparwood
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49737 in the federal list. How to read these figures.