Water and Wastewater Infrastructure Network Study

Sparwood, British Columbia

completeWastewaterCWWF
Federal contribution
$118,786
Federal share50%

of $237.6K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 17, 2017
2018
Built
Program
Clean Water and Wastewater Fund
Ultimate recipient
District of Sparwood
Construction start
Jul 17, 2017(actual)
Construction end
Jun 30, 2018(actual)

Against the original forecast

  • Construction start5 months lateforecast Feb 1, 2017
  • Construction end3 months lateforecast Mar 31, 2018

Also in Sparwood

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49846 in the federal list. How to read these figures.