Greenwood Wastewater Utility Renewal

Greenwood, British Columbia

completeWastewaterCWWF
Federal contribution
$349,486
Federal share50%

of $699.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 17, 2017
201820192020
Built
Program
Clean Water and Wastewater Fund
Ultimate recipient
City of Greenwood
Construction start
Oct 30, 2017(actual)
Construction end
Dec 31, 2019(actual)

Against the original forecast

  • Construction start3 months lateforecast Aug 1, 2017
  • Construction end3 months earlyforecast Mar 31, 2020

Also in Greenwood

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49756 in the federal list. How to read these figures.