Mesachie Lake Wastewater Treatment and Collection Upgrade Project, Phase 1 (Area F)

Honeymoon Bay, British Columbia

completeWastewaterCWWF
Federal contribution
$738,896
Federal share50%

of $1.5M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 17, 2017
201720182019202020212022
Built
Program
Clean Water and Wastewater Fund
Construction start
Nov 6, 2017(actual)
Construction end
Dec 3, 2021(actual)

Against the original forecast

  • Construction start13 months earlyforecast Dec 17, 2018