13th Avenue Water Line Upgrade
New Hazelton, British Columbia
Federal contribution
$396,512
Federal share50%
of $793.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 17, 2017
201820192020
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- District of New Hazelton
- Construction start
- Jul 31, 2017(actual)
- Construction end
- Mar 31, 2020(actual)
Also in New Hazelton