Lund Wastewater System Upgrade

Lund, British Columbia

completeWastewaterCWWF
Federal contribution
$280,000
Federal share50%

of $560.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 17, 2017
20182019
Built
Program
Clean Water and Wastewater Fund
Construction start
Jun 16, 2017(actual)
Construction end
Mar 31, 2019(actual)

Against the original forecast

  • Construction start3 months earlyforecast Sep 15, 2017

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49778 in the federal list. How to read these figures.