Electoral Area F - Hatzic Prairie Water System Upgrade

Hatzic, British Columbia

completeDrinking WaterCWWF
Federal contribution
$837,066
Federal share50%

of $1.7M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 20, 2017
20182019
Built
Program
Clean Water and Wastewater Fund
Construction start
Sep 15, 2017(actual)
Construction end
Oct 11, 2019(actual)

Against the original forecast

  • Construction start7 weeks earlyforecast Oct 31, 2017
  • Construction end6 months earlyforecast Mar 31, 2020

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49789 in the federal list. How to read these figures.