Wastewater System Upgrades

Mount Waddington, British Columbia

completeWastewaterCWWF
Federal contribution
$270,585
Federal share50%

of $541.2K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 17, 2017
20182019
Built
Program
Clean Water and Wastewater Fund
Construction start
Jul 17, 2017(actual)
Construction end
Mar 22, 2019(actual)

Against the original forecast

  • Construction end5 months lateforecast Oct 31, 2018

Also in Mount Waddington

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49793 in the federal list. How to read these figures.