Silverton Water Main Replacement

Silverton, British Columbia

completeDrinking WaterCWWF
Federal contribution
$214,344
Federal share50%

of $428.7K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 17, 2017
Built
Program
Clean Water and Wastewater Fund
Ultimate recipient
Village of Silverton
Construction start
May 22, 2017(actual)
Construction end
Dec 13, 2017(actual)

Against the original forecast

  • Construction start7 weeks lateforecast Apr 1, 2017
  • Construction end3 weeks lateforecast Nov 20, 2017

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49802 in the federal list. How to read these figures.