Silverton Water Main Replacement
Federal contribution
$214,344
Federal share50%
of $428.7K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 17, 2017
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Village of Silverton
- Construction start
- May 22, 2017(actual)
- Construction end
- Dec 13, 2017(actual)
Against the original forecast
- Construction start7 weeks lateforecast Apr 1, 2017
- Construction end3 weeks lateforecast Nov 20, 2017