Bamfield Water Treatment Facility

Bamfield, British Columbia

completeDrinking WaterCWWF
Federal contribution
$848,900
Federal share50%

of $1.7M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 17, 2017
2018
Built
Program
Clean Water and Wastewater Fund
Construction start
May 17, 2017(actual)
Construction end
Sep 30, 2018(actual)

Against the original forecast

  • Construction start4 months earlyforecast Sep 18, 2017
  • Construction end3 months lateforecast Jun 30, 2018

Also in Bamfield

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49803 in the federal list. How to read these figures.