Port Renfrew Water Main Replacement
Port Renfrew, British Columbia
Federal contribution
$292,290
Federal share50%
of $584.6K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 17, 2017
2018
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Regional District of Capital
- Construction start
- Sep 15, 2017(actual)
- Construction end
- Jan 31, 2018(actual)
Against the original forecast
- Construction start6 weeks earlyforecast Oct 27, 2017