Watermain Looping at Head of Lake

Oliver, British Columbia

completeDrinking WaterCWWF
Federal contribution
$280,755
Federal share50%

of $561.5K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 17, 2017
20182019
Built
Program
Clean Water and Wastewater Fund
Ultimate recipient
Town of Oliver
Construction start
Aug 15, 2017(actual)
Construction end
Mar 31, 2019(actual)

Against the original forecast

  • Construction start6 months earlyforecast Feb 26, 2018
  • Construction end5 months lateforecast Oct 31, 2018