Fort Fraser Infrastructure Improvement
Federal contribution
$1.9M
$1,856,429
Federal share50%
of $3.7M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 17, 2017
20182019
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Regional District of Bulkley-Nechako
- Construction start
- May 1, 2017(actual)
- Construction end
- Sep 30, 2019(actual)
Against the original forecast
- Construction start12 months earlyforecast May 7, 2018
- Construction end11 months lateforecast Nov 4, 2018
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49825 in the federal list. How to read these figures.