Fort Fraser Infrastructure Improvement

Fort Fraser, British Columbia

completeDrinking WaterCWWF
Federal contribution
$1.9M
$1,856,429
Federal share50%

of $3.7M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 17, 2017
20182019
Built
Program
Clean Water and Wastewater Fund
Construction start
May 1, 2017(actual)
Construction end
Sep 30, 2019(actual)

Against the original forecast

  • Construction start12 months earlyforecast May 7, 2018
  • Construction end11 months lateforecast Nov 4, 2018