Lake Baptiste Dam Upgrade

Edgewater, British Columbia

completeDrinking WaterCWWF
Federal contribution
$251,403
Federal share50%

of $502.8K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 17, 2017
20182019
Built
Program
Clean Water and Wastewater Fund
Construction start
Jun 1, 2017(actual)
Construction end
May 31, 2019(actual)

Against the original forecast

  • Construction start16 months earlyforecast Sep 24, 2018
  • Construction end10 months earlyforecast Mar 31, 2020

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49826 in the federal list. How to read these figures.