Rivervale and Oasis Sewer Service Pump Replacements

Kootenay Boundary, British Columbia

completeWastewaterCWWF
Federal contribution
$100,311
Federal share50%

of $200.6K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 17, 2017
2018
Built
Program
Clean Water and Wastewater Fund
Construction start
Apr 10, 2017(actual)
Construction end
Mar 14, 2018(actual)

Against the original forecast

  • Construction end2 weeks earlyforecast Mar 31, 2018

Also in Kootenay Boundary

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49830 in the federal list. How to read these figures.