Rivervale and Oasis Sewer Service Pump Replacements
Kootenay Boundary, British Columbia
Federal contribution
$100,311
Federal share50%
of $200.6K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 17, 2017
2018
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Regional District of Kootenay Boundary
- Construction start
- Apr 10, 2017(actual)
- Construction end
- Mar 14, 2018(actual)
Against the original forecast
- Construction end2 weeks earlyforecast Mar 31, 2018