Lagoon Aeration System - Phase II

Tumbler Ridge, British Columbia

completeWastewaterCWWF
Federal contribution
$535,300
Federal share50%

of $1.1M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 17, 2017
20182019
Built
Program
Clean Water and Wastewater Fund
Ultimate recipient
District of Tumbler Ridge
Construction start
Oct 9, 2017(actual)
Construction end
Dec 12, 2018(actual)

Against the original forecast

  • Construction start6 months earlyforecast Apr 15, 2018
  • Construction end6 weeks lateforecast Oct 31, 2018