Lagoon Aeration System - Phase II
Tumbler Ridge, British Columbia
Federal contribution
$535,300
Federal share50%
of $1.1M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 17, 2017
20182019
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- District of Tumbler Ridge
- Construction start
- Oct 9, 2017(actual)
- Construction end
- Dec 12, 2018(actual)
Against the original forecast
- Construction start6 months earlyforecast Apr 15, 2018
- Construction end6 weeks lateforecast Oct 31, 2018
Also in Tumbler Ridge
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49841 in the federal list. How to read these figures.