Electoral Area C Lake Errock Water System Upgrades
Federal contribution
$200,875
Federal share50%
of $401.8K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 17, 2017
2018
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Regional District of Fraser Valley
- Construction start
- Jul 15, 2017(actual)
- Construction end
- Mar 30, 2018(actual)
Against the original forecast
- Construction start6 months earlyforecast Jan 22, 2018
- Construction end4 weeks lateforecast Mar 1, 2018
Also in Lake Errock
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49882 in the federal list. How to read these figures.