Electoral Area C Lake Errock Water System Upgrades

Lake Errock, British Columbia

completeDrinking WaterCWWF
Federal contribution
$200,875
Federal share50%

of $401.8K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 17, 2017
2018
Built
Program
Clean Water and Wastewater Fund
Construction start
Jul 15, 2017(actual)
Construction end
Mar 30, 2018(actual)

Against the original forecast

  • Construction start6 months earlyforecast Jan 22, 2018
  • Construction end4 weeks lateforecast Mar 1, 2018