Kaslo Wastewater Treatment Plant Improvements

Kaslo, British Columbia

completeWastewaterCWWF
Federal contribution
$210,937
Federal share50%

of $421.9K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 17, 2017
2018
Built
Program
Clean Water and Wastewater Fund
Ultimate recipient
Village of Kaslo
Construction start
Mar 1, 2018(actual)
Construction end
Oct 31, 2018(actual)

Against the original forecast

  • Construction start12 months lateforecast Mar 1, 2017
  • Construction end7 months lateforecast Mar 31, 2018