Kaslo Wastewater Treatment Plant Improvements
Federal contribution
$210,937
Federal share50%
of $421.9K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 17, 2017
2018
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Village of Kaslo
- Construction start
- Mar 1, 2018(actual)
- Construction end
- Oct 31, 2018(actual)
Against the original forecast
- Construction start12 months lateforecast Mar 1, 2017
- Construction end7 months lateforecast Mar 31, 2018
Also in Kaslo
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49886 in the federal list. How to read these figures.