Beaver Valley Water System Davis/Eastview Improvements
Federal contribution
$108,150
Federal share50%
of $216.3K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 17, 2017
2018
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Regional District of Kootenay Boundary
- Construction start
- Jan 3, 2018(actual)
- Construction end
- Dec 1, 2018(actual)
Against the original forecast
- Construction start4 months earlyforecast Apr 23, 2018
- Construction end4 weeks lateforecast Nov 1, 2018
Also in Fruitvale
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49887 in the federal list. How to read these figures.