Water Reservoir Expansion

Bon Accord, Alberta

completeDrinking WaterCWWF
Federal contribution
$943,389
Federal share44%

of $2.2M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 6, 2017
20182019
Built

Approved 5 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
Town of Bon Accord
Construction start
May 7, 2018(actual)
Construction end
Sep 10, 2019(actual)

Against the original forecast

  • Construction end7 months earlyforecast Mar 31, 2020