Main Lift Station Upgrade
Federal contribution
$500,417
Federal share41%
of $1.2M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 6, 2017
20182019
Built
Approved 5 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Village of Alix
- Construction start
- Nov 5, 2018(actual)
- Construction end
- Aug 30, 2019(actual)
Against the original forecast
- Construction start3 weeks lateforecast Oct 15, 2018
- Construction end5 months lateforecast Mar 31, 2019
Also in Alix
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49924 in the federal list. How to read these figures.