Reservoir Addition

Delia, Alberta

completeDrinking WaterCWWF
Federal contribution
$537,500
Federal share50%

of $1.1M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 6, 2017
20182019
Built

Approved 5 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
Village of Delia
Construction start
Nov 5, 2018(actual)
Construction end
May 7, 2019(actual)

Against the original forecast

  • Construction start2 months lateforecast Sep 1, 2018
  • Construction end5 weeks lateforecast Mar 31, 2019

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49926 in the federal list. How to read these figures.