Myrnam Water Reservoir and Treatment Distribution Plant
Federal contribution
$678,168
Federal share42%
of $1.6M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 6, 2017
2018202020222024
Built
Approved 5 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Village of Myrnam
- Construction start
- Oct 1, 2023(actual)
- Construction end
- Jan 24, 2024(actual)
Against the original forecast
- Construction start18 months lateforecast Apr 1, 2022
- Construction end9 months earlyforecast Oct 31, 2024
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49928 in the federal list. How to read these figures.