Treated Water Reservoir and Pump System Upgrade

Granum, Alberta

completeDrinking WaterCWWF
Federal contribution
$504,466
Federal share44%

of $1.1M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 6, 2017
20182019
Built

Approved 5 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
Town of Granum
Construction start
Nov 1, 2017(actual)
Construction end
Jun 30, 2019(actual)

Against the original forecast

  • Construction start6 months earlyforecast May 15, 2018
  • Construction end4 weeks lateforecast May 31, 2019