Reconstruction of a sanitary building and rehabilitation of the infrastructures of the Saint-Jean-Bosco Park
Saint-Charles-Borromée, Quebec
Federal contribution
$68,333
Federal share33%
of $205.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 29, 2017
2018
Built
Approved 5 months before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- Municipality of Saint-Charles-Borromée
- Construction start
- May 1, 2018(actual)
- Construction end
- Nov 13, 2018(actual)
Against the original forecast
- Construction start12 months lateforecast May 1, 2017
- Construction end10 months lateforecast Dec 29, 2017