Reconstruction of a sanitary building and rehabilitation of the infrastructures of the Saint-Jean-Bosco Park

Saint-Charles-Borromée, Quebec

completeRecreationSCF
Federal contribution
$68,333
Federal share33%

of $205.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 29, 2017
2018
Built

Approved 5 months before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Construction start
May 1, 2018(actual)
Construction end
Nov 13, 2018(actual)

Against the original forecast

  • Construction start12 months lateforecast May 1, 2017
  • Construction end10 months lateforecast Dec 29, 2017