Water System Upgrades

Saint-Charles-Borromée, Quebec

completeWastewaterGIS
Federal contribution
$2.0M
$1,985,937
Federal share40%

of $5.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 17, 2020
202120222023
Built

Approved 4 months before the announcement.

Program
Green Infrastructure Stream
Construction start
Jun 28, 2021(actual)
Construction end
Mar 27, 2023(actual)

Against the original forecast

  • Construction end5 months lateforecast Oct 31, 2022