Back to projects

Replacement of the refrigeration system and upgrading of the municipal arena ventilation system

Sainte-Claire, Quebec

completeRecreationSCF
Federal contribution
$275,440
Federal share33%

of $826.3K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 25, 2017
20182019
Built

Approved 6 weeks before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Construction start
Nov 28, 2017(actual)
Construction end
Nov 12, 2019(actual)

Against the original forecast

  • Construction start5 months earlyforecast May 1, 2018
  • Construction end14 months lateforecast Sep 4, 2018