Water Systems Upgrades
Federal contribution
$1.1M
$1,086,802
Federal share40%
of $2.7M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 11, 2020
202120222023
Built
Approved 4 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Municipality of Sainte-Claire
- Construction start
- Apr 25, 2022(actual)
- Construction end
- Dec 20, 2022(actual)
Against the original forecast
- Construction start3 weeks lateforecast Apr 1, 2022
- Construction end3 weeks lateforecast Nov 30, 2022
Also in Sainte-Claire
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 56538 in the federal list. How to read these figures.