Replacement of 3 Transit operations vehicles and 4 hoists

Guelph, Ontario

completePublic TransitPTIF
Federal contribution
$436,037
Federal share41%

of $1.1M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedDec 8, 2017
2018201920202021
Built

Approved 7 months before the announcement.

Program
Public Transit Infrastructure Fund
Construction start
Jul 1, 2018(actual)
Construction end
Mar 31, 2021(actual)

Against the original forecast

  • Construction start2.2 years lateforecast Apr 1, 2016
  • Construction end4 months earlyforecast Jul 31, 2021

Also in Guelph

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49971 in the federal list. How to read these figures.