Capital 2017
Charlottetown, Prince Edward Island
Federal contribution
$595,499
Federal share50%
of $1.2M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedNov 14, 2017
2018
Built
Approved 4 months before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - National and Regional Projects
- Ultimate recipient
- Government of Prince Edward Island
- Construction start
- Aug 16, 2017(actual)
- Construction end
- Oct 15, 2018(actual)
Against the original forecast
- Construction start3 weeks earlyforecast Sep 4, 2017
- Construction end6 weeks lateforecast Aug 31, 2018
Also in Charlottetown
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49982 in the federal list. How to read these figures.