Back to projects

New Septage Disposal System

Indian Head No. 156, Saskatchewan

completeWastewaterCWWF
Federal contribution
$51,500
Federal share50%

of $103.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 2, 2017
2018
Built

Approved 6 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Construction start
Oct 13, 2017(actual)
Construction end
Jul 20, 2018(actual)

Against the original forecast

  • Construction end5 months earlyforecast Dec 31, 2018