Guernsey Water Supply and Treatment Upgrade

Usborne No. 310, Saskatchewan

completeDrinking WaterCWWF
Federal contribution
$181,125
Federal share50%

of $362.3K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 2, 2017
2018
Built

Approved 6 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Construction start
Sep 1, 2017(actual)
Construction end
Jul 16, 2018(actual)

Against the original forecast

  • Construction start4 weeks lateforecast Aug 1, 2017
  • Construction end2 weeks lateforecast Jun 30, 2018

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 50002 in the federal list. How to read these figures.