Guernsey Water Supply and Treatment Upgrade
Federal contribution
$181,125
Federal share50%
of $362.3K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 2, 2017
2018
Built
Approved 6 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Rural Municipality of Usborne No. 310
- Construction start
- Sep 1, 2017(actual)
- Construction end
- Jul 16, 2018(actual)
Against the original forecast
- Construction start4 weeks lateforecast Aug 1, 2017
- Construction end2 weeks lateforecast Jun 30, 2018