New Wastewater Pump Station
Federal contribution
$121,060
Federal share50%
of $242.1K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 2, 2017
2018
Built
Approved 6 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Rural Municipality of Waverley No. 44
- Construction start
- Jul 15, 2017(actual)
- Construction end
- Mar 31, 2018(actual)
Against the original forecast
- Construction start7 months earlyforecast Feb 15, 2018
- Construction end9 months earlyforecast Dec 31, 2018
Also in Waverley No. 44