New Wastewater Treatment System
Federal contribution
$1.4M
$1,418,800
Federal share50%
of $2.8M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 2, 2017
201820192020
Built
Approved 6 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Town of Bienfait
- Construction start
- May 25, 2018(actual)
- Construction end
- Feb 27, 2020(actual)
Against the original forecast
- Construction end10 months lateforecast Apr 30, 2019
Also in Bienfait
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 50010 in the federal list. How to read these figures.