Stormwater System Upgrade

Bruno, Saskatchewan

completeWastewaterCWWF
Federal contribution
$211,500
Federal share50%

of $423.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 2, 2017
Built

Approved 6 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
Town of Bruno
Construction start
Sep 25, 2017(actual)
Construction end
Oct 30, 2017(actual)

Against the original forecast

  • Construction start4 months lateforecast Jun 1, 2017
  • Construction end8 months earlyforecast Jun 30, 2018

Also in Bruno

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 50012 in the federal list. How to read these figures.