Stormwater System Upgrade
Federal contribution
$211,500
Federal share50%
of $423.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 2, 2017
Built
Approved 6 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Town of Bruno
- Construction start
- Sep 25, 2017(actual)
- Construction end
- Oct 30, 2017(actual)
Against the original forecast
- Construction start4 months lateforecast Jun 1, 2017
- Construction end8 months earlyforecast Jun 30, 2018
Also in Bruno
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 50012 in the federal list. How to read these figures.