Water Treatment System Upgrade
Federal contribution
$66,488
Federal share50%
of $133.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 2, 2017
2018
Built
Approved 6 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Town of Canora
- Construction start
- Jan 8, 2018(actual)
- Construction end
- Sep 28, 2018(actual)
Against the original forecast
- Construction start5 weeks lateforecast Dec 1, 2017
- Construction end3 months lateforecast Jun 30, 2018
Also in Canora
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 50013 in the federal list. How to read these figures.