Wastewater Pump Station Upgrade

Choiceland, Saskatchewan

completeWastewaterCWWF
Federal contribution
$48,050
Federal share50%

of $96.1K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 2, 2017
2018
Built

Approved 6 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
Town of Choiceland
Construction start
Sep 1, 2017(actual)
Construction end
Mar 5, 2018(actual)

Against the original forecast

  • Construction start3 months lateforecast Jun 15, 2017
  • Construction end8 weeks earlyforecast May 3, 2018

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 50014 in the federal list. How to read these figures.