Dixon Hall Youth Centre
Federal contribution
$250,000
Federal share5%
of $5.2M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedNov 8, 2017
201820192020
Built
Approved 6 months before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - National and Regional Projects
- Ultimate recipient
- Dixon Hall Neighbourhood Services
- Construction start
- Oct 15, 2018(actual)
- Construction end
- Feb 14, 2020(actual)
Against the original forecast
- Construction start14 months lateforecast Aug 1, 2017
- Construction end16 months lateforecast Sep 30, 2018
Also in Toronto
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 50021 in the federal list. How to read these figures.