Dixon Hall Youth Centre

Toronto, Ontario

completeRecreationNRP
Federal contribution
$250,000
Federal share5%

of $5.2M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedNov 8, 2017
201820192020
Built

Approved 6 months before the announcement.

Program
Provincial-Territorial Infrastructure Component - National and Regional Projects
Construction start
Oct 15, 2018(actual)
Construction end
Feb 14, 2020(actual)

Against the original forecast

  • Construction start14 months lateforecast Aug 1, 2017
  • Construction end16 months lateforecast Sep 30, 2018

Also in Toronto

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 50021 in the federal list. How to read these figures.