Drinking water installation at the Harkness Laboratory, Algonquin Park

Sproule, Ontario

completeDrinking WaterCWWF
Federal contribution
$12,620
Federal share42%

of $30.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 7, 2017
Built

Approved 7 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Construction start
Oct 17, 2017(actual)
Construction end
Nov 24, 2017(actual)

Against the original forecast

  • Construction start7 months lateforecast Apr 1, 2017
  • Construction end4 months earlyforecast Mar 31, 2018

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 50026 in the federal list. How to read these figures.