Water Distribution System Upgrade
Federal contribution
$51,666
Federal share50%
of $103.3K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 2, 2017
Built
Approved 6 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Town of Hanley
- Construction start
- Sep 5, 2017(actual)
- Construction end
- Oct 27, 2017(actual)
Against the original forecast
- Construction start2 months lateforecast Jul 3, 2017
- Construction end5 months earlyforecast Mar 31, 2018
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 50036 in the federal list. How to read these figures.