Water Distribution System Upgrade

Hanley, Saskatchewan

completeDrinking WaterCWWF
Federal contribution
$51,666
Federal share50%

of $103.3K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 2, 2017
Built

Approved 6 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
Town of Hanley
Construction start
Sep 5, 2017(actual)
Construction end
Oct 27, 2017(actual)

Against the original forecast

  • Construction start2 months lateforecast Jul 3, 2017
  • Construction end5 months earlyforecast Mar 31, 2018

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 50036 in the federal list. How to read these figures.