Water Treatment Plant and Reservoir Upgrade
Federal contribution
$100,000
Federal share50%
of $200.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 2, 2017
Built
Approved 6 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Town of Mossbank
- Construction start
- Sep 18, 2017(actual)
- Construction end
- Nov 23, 2017(actual)
Against the original forecast
- Construction start2 weeks lateforecast Sep 4, 2017
- Construction end4 months earlyforecast Mar 31, 2018