Water Tower Rehabilitation
Federal contribution
$77,805
Federal share50%
of $155.6K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 2, 2017
Built
Approved 6 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Town of QuAppelle
- Construction start
- Oct 1, 2017(actual)
- Construction end
- Oct 26, 2017(actual)
Against the original forecast
- Construction end17 months earlyforecast Mar 31, 2019