Lift Station Upgrade

Rocanville, Saskatchewan

completeWastewaterCWWF
Federal contribution
$127,250
Federal share50%

of $254.5K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 2, 2017
201820192020
Built

Approved 6 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
Town of Rocanville
Construction start
May 31, 2018(actual)
Construction end
Feb 20, 2020(actual)

Against the original forecast

  • Construction end6 weeks earlyforecast Mar 31, 2020