Sewage Pump Station #2 Replacement
Federal contribution
$81,880
Federal share50%
of $163.8K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 2, 2017
201820192020
Built
Approved 6 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Town of Wawota
- Construction start
- Nov 25, 2019(actual)
- Construction end
- Dec 20, 2019(actual)
Against the original forecast
- Construction start13 months lateforecast Oct 15, 2018
- Construction end10 months lateforecast Feb 20, 2019
Also in Wawota
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 50052 in the federal list. How to read these figures.