Water Treatment Plant Expansion and Upgrade
Federal contribution
$200,000
Federal share50%
of $400.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 2, 2017
20182019
Built
Approved 6 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Village of Creelman
- Construction start
- May 30, 2017(actual)
- Construction end
- Mar 31, 2019(actual)
Against the original forecast
- Construction start5 months earlyforecast Oct 31, 2017
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 50057 in the federal list. How to read these figures.