Wastewater Pump Station Upgrade

Macnutt, Saskatchewan

completeWastewaterCWWF
Federal contribution
$9,000
Federal share50%

of $18.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 2, 2017
2018
Built

Approved 6 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
Village of Macnutt
Construction start
Sep 3, 2018(actual)
Construction end
Dec 4, 2018(actual)

Against the original forecast

  • Construction start2 months lateforecast Jul 1, 2018
  • Construction end4 months earlyforecast Mar 31, 2019

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 50065 in the federal list. How to read these figures.