Back to projects

Water Treatment Plant Upgrades

Weirdale, Saskatchewan

completeDrinking WaterCWWF
Federal contribution
$15,000
Federal share50%

of $30.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 2, 2017
201820192020
Built

Approved 6 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
Village of Weirdale
Construction start
Sep 4, 2018(actual)
Construction end
Nov 29, 2019(actual)

Against the original forecast

  • Construction end9 months lateforecast Mar 15, 2019

Also in Weirdale