Water Treatment Plant System Upgrades
Federal contribution
$130,979
Federal share50%
of $262.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 2, 2017
20172018
Built
Approved 6 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Village of Welwyn
- Construction start
- Jul 19, 2016(actual)
- Construction end
- Dec 14, 2017(actual)
Against the original forecast
- Construction start8 months earlyforecast Apr 1, 2017
- Construction end11 months earlyforecast Oct 31, 2018