Replace culverts and raise the grade of Leighton Road at various locations

Machar, Ontario

completeWastewaterCWWF
Federal contribution
$50,000
Federal share50%

of $100.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 24, 2017
Built

Approved 2 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
Township of Machar
Construction start
Jun 1, 2017(actual)
Construction end
Oct 31, 2017(actual)

Against the original forecast

  • Construction start2 months lateforecast Apr 1, 2017
  • Construction end4 weeks earlyforecast Nov 30, 2017

Also in Machar

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 50075 in the federal list. How to read these figures.